In a significant judgment, the Supreme Court of India addressed the issue of delay in delivering possession of flats by developers and the compensation due to buyers. The case, Vidya and Others vs. M/S Parsvnath Developers Ltd., highlights the importance of consumer rights in real estate transactions and the obligations of developers to adhere to promised timelines.
The appeal stemmed from an order by the National Consumer Disputes Redressal Commission (NCDRC), which directed Parsvnath Developers Ltd. to refund the amount deposited by the complainants, Vidya and others, with interest. Here's a detailed look at the facts leading up to the appeal:
Project Launch and Initial Payments
Payment Plan and Subsequent Issues
Legal Action and Commission's Order
The appellants challenged the NCDRC's order, particularly the interest rate of 9% per annum, arguing it should be higher given the terms of the Flat Buyer Agreement and the significant delay.
Arguments Presented
Court's Findings
The Supreme Court, citing precedents and the specifics of the case, held that:
"Insofar as the contention of the respondent-Developer that since there was a delay in sanctioning the layout plans, it was covered under force majeure clause is concerned, this Court, in the case of DLF Home Developers Limited (earlier known as DLF Universal Limited) and Another v. Capital Greens Flat Buyers Association and Others has held to the contrary."
The court found that the NCDRC rightly directed the refund but should have awarded a higher interest rate given the circumstances:
"In our view, the learned Commission, at least, ought to have awarded interest at the rate of 12% per annum in view of clause 7(b) of the Agreement."
The Supreme Court partly allowed the appeal, modifying the interest rate:
"The direction made by the learned Commission for refund of the entire amount deposited by the complainants-appellants is upheld. However, the direction with regard to interest is modified to the extent that it shall be paid at the rate of 12% per annum from the date of respective deposit till the date of refund."
The judgment underscores the court's commitment to protecting consumer rights and ensuring developers fulfill their contractual obligations.
TAGS: Consumer rights Supreme Court Delay compensation Real estate Refund Interest rate NCDRC